
|
 |

|
About the Author... |
|

David Kemei is the Financial Analyst for the Electricity Regulatory Board
of Kenya. He is primarily responsible for the assessment of financial
performance and the strategic financial issues of utilities in the electricity
sub-sector. Mr. Kemei is an IP3 Alumnus, Certified Regulation Specialist, and
Certified Public Accountant. He holds an MBA and Bcom from the University of
Nairobi in Kenya. |
|
Operation Costs and Capital Expenditure
in Kenya's Electricity Sub-Sector
By David Kemei
|
Abstract |
This article, by IP3 Alumnus David
Kemei, traces the steps and outcomes of a study carried out by the Electricity
Regulatory Board (ERB) in Kenya to determine reasonable operating costs and
capital expenditures for the country's electricity utilities.
INTRODUCTION
In Kenya, the electricity sub-sector
falls under the Ministry of Energy (MOE), which is responsible for energy
policy formulation and oversight of the organizations in the power and
petroleum sub-sectors. In addition, the MOE facilitates regulation, monitoring
and coordination of activities undertaken by the sector players, promotes
technological advancement and provides stimulus to investment and growth in the
sub-sector. |
In the early 1990s, the Government of Kenya
(GoK) undertook major energy policy and institutional reforms to address the
imminent challenges that faced the energy sector and electricity sub-sector in
particular. These policy initiatives and reforms led to the unbundling of
generation from transmission and distribution of electricity and the creation
of the Electricity Regulatory Board (ERB) through an act of parliament,
Electric Power Act, 1997. These reforms continue to be implemented and at the
moment, all public generating assets (which were previously owned by regional
development authorities) are consolidated under Kenya Electricity Generating
Company (KenGen) which recently sold its 30% of shares to the public leaving
the balance of 70% in the hands of the Kenya Government. The transmission and
distribution assets are consolidated under Kenya power & Lighting Company
(KPLC) effectively making a single buyer model.
These reforms paved the way for an inflow
of capital into the electricity sub-sector from private sector investors. At
present there are three Independent Power Producers (IPPs) namely, Iberafrica,
OrPower 4 and Tsavo power that are owned and operated by private investors.
These IPPs generate and feed electricity into the national grid. This article
traces the steps and outcomes of one of the studies carried out in 2002 by ERB
in its quest to determine the reasonableness of Operating Costs and Capital
Expenditure reported by the electricity sub-sector utilities mentioned above.
BACKGROUND
Pursuant to Energy Sector Policy Framework
Papers of 1992-1995 and 1996-1998 the Government of Kenya initiated power
sector reforms aimed at creating arm's length commercial type-relationships
between the electricity sub-sector entities and created the legal and
regulatory framework that would facilitate the envisioned restructuring of the
electricity sub-sector and encourage private sector participation. The
generation sector is now fully liberalized with KenGen being the dominant
player with the current interconnected effective capacity of 892 MW compared
with IPPs combined effective capacity of 145 MW. These power producers sell
electricity in bulk, under Power Purchase Agreements, which were approved by
ERB, to KPLC for onward transmission (at 220 and 132kV), distribution (at
11-66kV) and supply (at 240-415V). KPLC is also responsible for dispatch of
generation and system operation. These reforms resulted in the establishment of
ERB as an independent electricity regulator in Kenya through an act of
parliament to:
- Set, review and adjust tariffs for all entities who
transmit or distribute electrical energy for sale,
- Investigate tariff structure even when no specific
application for tariff adjustment has been made,
- Enforce environmental and safety regulations in the
power sub-sector,
- Investigate complaints made by parties with grievances
over any matter required to be regulated under the act
- Ensure that there is genuine competition where this is
expected, and
- Approve electric power purchase contracts and
transmission and distribution service contracts between and among electric
power producers, public electricity suppliers and large retail customers.
There are plans to expand the mandate of
ERB to include regulation of the petroleum sub-sector.
The act requires ERB to ensure that no
particular person or entity is given undue
preference or subjected to any undue
disadvantages when carrying out its legal mandate. In addition, it requires the
Board to ensure that tariffs are just and reasonable. ERB is also obligated by
the act to ensure that investors earn a reasonable return on their investments
in the electricity sub-sector by taking into account the ability of the
licensee to maintain its financial integrity, attract capital, operate
efficiently, and fully compensate investors for the risks assumed.
The existing tariffs, whose basis was the
1997 tariff study commissioned and funded by the World Bank, was approved by
the ERB and came into effect on 1st August 1999. The ERB approved base tariffs
and pass through elements related to monthly fuel costs and fluctuations in
foreign denominated costs that vary every month.
The ERB then embarked on a tariff policy
review exercise that culminated in a stakeholder workshop where the ERB engaged
stakeholders in the electricity sub-sector to dialogue and capture the
stakeholder's needs and concerns regarding the new tariff policy. This stakeholder workshop included training on best practices in
tariff review and the requirements of 1997 Electric Power Act. It was at this
meeting that stakeholders impressed upon the ERB the need for tariffs that
reflect only costs of efficient operation and prudent projections of capital
expenditures by utilities in electricity sub-sector. ERB found itself in the
unenviable, but mandated situation of balancing the divergent needs of its
stakeholders.
Objectives of the Study
Following the aforementioned
stakeholder workshop, ERB commissioned an independent study to establish the
appropriate levels of operation costs and capital expenditure in electricity
sub-sector. The main objective of the study was that the ERB aimed to establish
tariffs that accurately reflect the costs of efficient operation of generation,
transmission and distribution as well as prudent future capital expenditure to
cater for load growth, replacement and refurbishment of capital assets as well
as reduction of losses. The other objectives of the study were:
- Establishing the prudence of projected operating and
maintenance cost, including underlying assumptions and benchmarking against
similar entities elsewhere in the world;
- Establishing the reasonableness of projected capital
expenditure, including relevant assumptions, based on realistic future
development targets for the electricity sub-sector;
- Quantifying potential savings in power production
costs;
- Benchmarking of the operational costs and performance of
utilities in Kenya against other utilities in the world that operate with
similar operating environment;
- Considering the above, recommend appropriate levels of
power purchase costs, operating and maintenance costs and capital expenditure
to be included in formulating tariffs;
- Propose practical ways for the monitoring, by ERB, of
the approved levels of the costs, and
- Determine objective and non-discriminatory merit order
of dispatch.
Scope of Work
In order to achieve the above stated
objectives, the scope of work was designed to include the following tasks:
- Detailed study of recent and past operating costs
incurred by utilities in Kenya and the extent to which utilities are employing
best practices in running their respective businesses.
- Based on determined efficient operation of power plants,
derive an objective and non-discriminatory merit order of dispatch of available
generation capacity,
- Detailed review and advise on the prudence of the
projected costs of utilities including the scope of potential savings from
efficiency improvements,
- Carry out critical scrutiny of utilities proposals for
capital expenditure with a view to establishing their reasonableness and
advising on the appropriate levels of investments needed for replacement and
refurbishment of ageing assets, to increase efficiency, reduce losses, and to
meet new load growth,
- Categorize capital expenditure into growth-related and
non-growth related and investigate whether design standards applicable to
system expansion are consistent with loss reduction and quality of service
projects on the system, and
Review assumptions made in arriving at
projected future operational costs and capital expenditures.
Study Outcomes
The study into the projected capital and
operating expenditure of utilities in the electricity sub-sector in Kenya
commenced in June 2002 and was finalized in November 2002. The findings of this
study are summarized below:
- KenGen - The study identified specific KenGen plants that
do require future capital expenditure and some that do not. Operating costs at
some KenGen power stations appeared high in comparison to international norms,
and the study recommended measures to reduce these costs.
- KPLC - The study revealed that KPLC's transmission costs
conformed to reasonable costs in developing countries. However, the utility's
systems need significant capital investment due to long periods of under
investment, and concluded that forecasts for distribution system capital
expenditure were inadequate to provide for loss reduction. The study also
showed that in terms of operating efficiency, KPLC was less efficient compared
to similarly sized utilities in Ecuador, Jamaica, and Europe. At the time of
the study, losses on the KPLC system stood at 21.3% segregated into technical
losses at 15.4% and non technical losses at 5.9% which were higher than would
be expected for an efficiently designed and operated network of the size of the
Kenyan system. Since the study, there has been an improvement in total system
losses to 18.1%.
- IPPs - The study found that there were no forecast
capital expenditures for the IPPs. The consultants found operating expenditures
provided by IPPs to be reasonable, but were unable to quantify the savings that
would be accruing from more efficient dispatch.
- The study found several inconsistencies in the way
utilities capture and report data, and recommended a uniform system of data
reporting, to simplify and improve ERB's monitoring function.
Overall, the study unearthed and opened an
eye to the regulator on what goes on in reported operating expenditures. The
report and findings of the study were discussed and adopted at yet another
stakeholders' forum.
Conclusion
To succeed in regulation of electricity
sub-sector in Kenya, we at ERB subscribe to the tenets of best practice in
every aspect of regulation and we go to great lengths to acquire the necessary
tools and resources to make it a reality. ERB has not perfected the art of best
practice in regulation but it is putting in a lot of effort to improve in areas
of weakness. Since best practice in regulation is the backbone of its
philosophy, ERB provided a forum to dialogue with stakeholders on its draft
tariff review policy. ERB recognized her limitation of lack of capacity to
carry out the assignment, and made the strategic decision to engage a
consultant to carry out the independent study.
For further information on the activities
of Electricity Regulatory Board (ERB) of Kenya, kindly visit
www.erb.go.ke. Or feel free to contact the
author, Mr. David Kemei, Financial Analyst, at
david.kemei@erb.go.ke.
Copyright 2006© Institute for
Public-Private Partnerships, Inc. All rights reserved
Home |
About IP3 |
Training |
Consulting
Alumni
Corner | e-Newsletter | Careers |
Site Index |
Links |
Contact
|