|

|
About the Author...  |
|
James Moses Omara-Ogwang is a Compliance Engineer and acting Manager of
Technical Regulation at the Electricity Regulatory Authority of Uganda. His
work entails ensuring, through inspections, that Licensees in the electricity
sector abide by their license obligations, observe applicable standards, and
operate according to good professional practice. He also advises investors
intending to join the electricity sector in Uganda. Mr. Omara is an IP3
alumnus. |
|
Establishing a Benchmarking System:
Achievements and Lessons Learned from the Uganda Electricity Sector
James Moses
Omara-Ogwang
|
Abstract |
The electricity sector in Uganda was
unbundled in 2001 by passing into law a new Electricity Act in 1999. This Act
also provided for the formation of the Electricity Regulatory Authority (ERA)
in 2001. The Act provided for ERA's functions, which were premised on
regulating the newly restructured electricity sector. Because of this, ERA had
to develop key performance indicators to be used in a benchmarking system as
part of the regulatory process. This involved undergoing a protracted
consultation process with the key stakeholders in the electricity
sector.
|
I. Introduction
"Agreements get better results than
Arguments." (Anonymous)
The Electricity Act, 1999¹ , besides
liberalising and privatising the electricity sector as its main thrust, also
provided for the formation of the Electricity Regulatory Authority (ERA) in
Uganda. As a consequence ERA was formed in 2000, and the then vertically
integrated electricity utility, Uganda Electricity Board (UEB), was unbundled
into independent generation, transmission and distribution companies in 2001.
The Act provided for the functions of ERA, one of which is:
"To
develop and enforce performance standards for the generation, transmission and
distribution of electricity" (The Electricity Act, 1999, S11
(i))
Because of this mandate ERA resolved to develop a benchmarking
system that could be uniformly applied in the electricity sector. This article
attempts to summarise the experience ERA has gone through to establish the
benchmarking system up to the point where it is on the verge of being launched,
as well as the lessons learned.
The Beginning
ERA did not go straight into preparing and
rolling out the benchmarking system but established a Reporting Schedule (RS)
in 2003 that contained a set of reporting requirements for Licensees² .
This was a template through which the Licensees could report on their licensed
activities and was supposed to be filled in and submitted quarterly.
The RS enabled ERA to keep track of the
licensed activities of the Licensees through establishment of trends. It did
not incorporate a system of measuring their performance.
It is
important to point out that prior to the issuing out of the RS's, ERA was still
receiving reports from the Licensees though in an un-coordinated manner. The
RS's were meant to provide a uniform format which the Licensees could follow
thus making it easier for ERA to extract the required information.
ERA
subsequently agreed with the Licensees that, as a means of making the RS's more
meaningful and useful to all the stakeholders, a set of key performance
indicators (KPI) should be drawn up, which would be worked out from the data
coming through the RS's. ERA could then use these indicators to measure the
performance of the Licensees, and even publish them publicly.
The Consultation Process
for the Reporting Schedules (RS's) and Key Performance Indicators (KPI)
Preparing the Reporting
Schedules
Prior to the launch of the RS's and KPI's
there were a series of consultation processes that ERA had to go through with
the Licensees, and also the wider public³ this time.
At the first consultation level, ERA
engaged a consultant to draw up a template that would eventually be developed
into the RS. To achieve this, the consultant had to have an idea of what kind
of information ERA wanted to obtain from the Licensees as well as the
information that the Licensees actually had. It also had to incorporate
technical, commercial and financial information, which would be summarised to a
level that made them not onerous to the Licensees but at the same time
contained all the information that ERA required. This was not a simple
balancing act!
The result was a set of RS's that ERA
presented to the Licensees and the wider public in series of workshops at the
second consultation level. These workshops had three aims:
- Receive ideas from the Licensees on how the schedules
could be made more user-friendly.
- To agree on the final template to be used by the
Licensees
- To establish the responsibility levels for preparing and
submitting these reports
All parties agreed that it was important
that an appropriate responsibility level be established for the RS's so that
Licensees would take them seriously. It was therefore agreed that the top
management in each organisation would take responsibility for having the RS
templates filled in, endorsed and submitted to ERA in good time. I'm glad to
note that this is still working well up to now.
After the workshops the RS's were agreed
upon and adopted. It is also in one of these workshops (the last one!) that the
idea of drawing up key performance indicators was flagged off. It was suggested
that a list of benchmarks that could be applied to the Ugandan electricity
sector be drawn up and these benchmarks would be worked out from the data
provided in the RS's. Note that the Reporting Schedules have not been discarded
at all! Instead they are being refined to enable better and more accurate
capture of data.
Drawing up the Indicators
At the third consultation level in 2004,
ERA engaged a consultant to examine the RS as well as other internationally
accepted indicators and come up with a set of KPIs that could be incorporated
into the benchmarking system we intended to adopt. Here again the consultant
had to perform a serious balancing act! The following issues had to be dealt
with:
- The KPI's had to be worked out from the already existing
RS's
- These KPI's had to have a "local flavour" yet be
internationally competent
- The KPI's had to be few but enough to provide a fair
measure of the performance of the Licensees
The consultant proposed a set of 45
indicators from 10 "measurement areas" of the electricity sector. These were
increased to 62 after adding indicators that were "peculiar" to the local
situation but which could not be benchmarked internationally. Stakeholders
debated the initial list of KPI's in a workshop at the fourth consultation
level. The result of this debate was a final list of 53 indicators, which
included commercial, technical and financial indicators. This number is not
fixed and is subject to change after revising the benchmarking system in
future!
Subsequently stakeholders agreed that the
financial reporting as it stood in the RS was sufficient for monitoring the
performance of the Licensees hence the financial indicators were dropped from
the list of indicators drawn up. This cut down the number of indicators to 38
consisting of: 27 for the distribution companies; 9 for the transmission
companies; and 2 for the generation companies. These KPI's would be worked out
from the data that the companies presented in the RS's and published in an
agreed format.
These KPI's together with the RS's that
provide the data for working them out have now constituted ERA's benchmarking
system4 .
Lessons Learned
The entire process of developing first,
the Reporting Schedules, then the Performance Indicators has provided some
important learning points that are worth sharing.
- One does not have to go straight into applying KPI's but
can progress slowly from an acceptable reporting system. It is always important
to have it at the back of our minds that while the KPI's are important and
useful they are not an end to themselves. Other means of tracking performance
can be equally useful.
- Operators do not necessarily want internationally
accepted indicators to benchmark against. As a matter of fact most would prefer
home grown indicators that they can easily identify with.
- It is important to agree on an acceptable number of
indicators with the target stakeholders. There is a benchmark of the acceptable
number of indicators but this number can be varied depending on the system
being monitored and what the stakeholders find acceptable.
- The target stakeholders need to be consulted at each and
every stage to make the indicators acceptable to them.
- The RS's were drawn mainly with the major players in the
Ugandan electricity sector in mind. There are, however, some smaller players
(mini-hydro plants) in existence, and a few others are in the pipeline. These
have expressed a concern that the RS's are too big and complex for their small
operations. While bearing in mind the negative effect of proliferating RS's,
their concerns are being addressed.
- In introducing KPI's, stakeholders should not be
burdened with reporting requirements. "Reporting fatigue" can easily lead to
stakeholders furnishing false data hence rendering the entire benchmarking
system useless!
III.
¹ The full Act can
be found at ERA's website, http://www.era.or.ug .
²
Licensees are companies that have been granted licences by ERA to operate in
the electricity sector at generation, transmission, and distribution levels of
the main grid, or to operate isolated grids.
³ These were
selected from key companies, institutions and individuals that have a role to
play in the electricity sector, or have keen interest in the business of the
sector.
4This kind of neatly
solved the vexing problem of how to gather useful data consistently for the
benchmarking system!
Copyright 2006© Institute for
Public-Private Partnerships, Inc. All rights reserved
Home |
About IP3 |
Training |
Consulting
Alumni
Corner | e-Newsletter | Careers |
Site Index |
Links |
Contact
|