About the Author...  |
|
Chavan Dabeedin is the Senior Strategic Projects and Research Analyst at the
Central Electricity Board (CEB) in Mauritius. He is primarily responsible for
providing leadership and direction in the development and implementation of
strategies, plans and actions required for CEB to succeed as a viable business.
Mr. Dabeedin is an IP3 Alumnus, and holds a B-Tech (Hons) in Mechanical
Engineering, and MBA, and a MSc. in Electrical Power Systems from the
University of Bath in the United Kingdom. |
|
Electricity Reform in Mauritius: The
Case of PSP in Generation
Chavan Dabeedin
|
Abstract |
From 2000-2005, the Government of
Mauritius embarked on a series of reforms in the electricity sector including
the corporatization of the Central Electricity Board (CEB), the country's
electric utility. A change in government in 2005, however, brought with it
alternative plans for reforming the sector. In this article, IP3 Alumnus,
Chavan Dabeedin describes the development and change in the government's
reform strategies, and discusses it's decision and method for leveraging the
resources of the private sector in the electricity generation, while
maintaining the status of CEB as a parastatal entity.
Brief History of the Central
Electricity Board
The Central Electricity Board is a
parastatal body wholly owned by the Government of Mauritius, under the aegis of
the Ministry of Public Utilities. Established on 8th December 1952 and
empowered by the Central Electricity Board Act of 25 January 1964, CEB's
business is to "prepare and carry out development schemes with the general
object of promoting, coordinating and improving the generation, transmission,
distribution and sale of electricity" in Mauritius. |
At the time of Independence in 1968, the
national rural electrification program got underway. Peak demand that year
reached 31 MW and total energy sales to 91,234 customers reached 98 GWh. As the
population increased and habitations cropped up all over the island, CEB was
called on to connect schools, Central Water Authority pumping stations, housing
estates and morcellements (parcelling of land for housing construction). Stone
crushing plants, poultry farms, irrigation stations, and construction sites
also appeared on the list of CEB's customers. From the early 1970s, CEB
networks have continuously been extended to supply new industries such as those
in the export processing zones. As the tourist sector, the textile industry,
and the construction sector flourished in the 1980s, CEB expanded its
transmission and distribution networks in all directions across the country. By
1981, the national rural electrification program was completed and the whole
island was 100% electrified.
Today with a workforce of approximately
1700 employees, CEB safely and dependably delivers electricity to more than
357,000 customers through 7,300 km of distribution network. Sales reached 1741
GWh in 2005 and the system peak demand has risen to more than 353 MW. Today,
the country enjoys a more diversified economy, an extensive network of
electricity supply facilities, and the benefits of a stable and continuous
electricity supply. CEB has a proven record of providing reliable electricity
for the country and this has come as a result of massive capital investment
into the development of electricity infrastructure. In 2005, the CEB itself
generated about 58 percent of electricity for the country's requirements - from
its four thermal power stations and eight hydroelectric plants, which have a
combined capacity of 367 MW. The remaining 42 percent of energy requirements
was purchased from independent power producers (IPP), which have a total firm
capacity of 147 MW and produce electricity from coal and bagasse (residue when
sugar juice is extracted from sugar cane). The generation mix is shown in
figure 1 below.
Figure 1: Electricity
Generation Mix in 2005

Background of Government Reform
Initiatives
From 2000-2005, the Government of Mauritius
embarked on a series of sector reforms under which it would retain overall
responsibility for essential public services, such as the provision of
electricity, but at the same time implement the necessary legal and
administrative steps with a view to moving the Central Electricity Board (CEB),
the national electricity utility of Mauritius, from a parastatal body to a
corporate entity. Having the CEB operate as a corporate entity operating
according to sound business principles-while remaining fully owned by
Government-would have allowed the Government to free up precious financial
support and resources for other public needs.
In meeting its social obligations as
electricity provider to a rapidly growing island nation, the Central
Electricity Board has not always been able to operate on commercial principles.
This has contributed to a weak financial position for the utility over the
years. Given that the country is now completely electrified and the standard of
living have risen for a majority of the population, CEB may now envisage to
balance its social obligations with operations as a commercial entity.
To realise its plans for the sector, the
Government of Mauritius committed in October 2000 to improve the financial
condition of the sector through improvements in efficiency, reductions in
system expansion costs, and injection of fresh capital through private
participation by taking the following distinct steps:
- Corporatise the CEB as a vertically-integrated
utility;
- Set up an independent, multi-sectoral regulator;
and
- Invite a strategic partner to assist in the management
of the CEB.
However, the policy of the new government,
which took over in July 2005, while also geared towards a self-sustaining
electricity sector, was not necessarily committed to the corporatization of the
CEB or the invitation of a strategic partner to assist its management.
 |
Mauritius Population: 1.2 million GDP per
capita: Purchasing power parity: $13,300 (2005 est.), highest in
Africa Geography: an island in the Indian Ocean grouped with Southern
Africa Development Community (SADC), also member of the Common Market for
Eastern and Southern Africa (COMESA), and Common Wealth Languages:
English, French (both official), Hindi & Creole Ethnicity/race:
Indo-Mauritian 68% (Indian origin), Creole 27% (African origin), Sino-Mauritian
3% (Chinese origin), Franco-Mauritian 2% (French origin) Religions:
Hindu 52%, Christian 28.3% (Roman Catholic 26%, Protestant 2.3%), Islam 16.6%,
others 3% Politics: Stable & Democratic
|
New Government Reform
Initiatives
The previous Government of Mauritius
(2000-2005)-and more so the new government-after watching the extent and
outcome of reforms in other countries, wisely recognised that Mauritius is
neither ready for, nor in need of, large-scale electricity reform. In general,
reforms elsewhere were intended to reduce costs to customers by making the
sector more competitive. Vertically integrated electricity monopolies have
typically been separated into generation, transmission, and distribution
entities. Of these, typically only generation and distribution have been
privatised and competition induced by dividing these entities into multiple
companies. To function properly, competitive markets require many buyers and
sellers. On an island the size of Mauritius-there are no economies of scale to
be gained by such division. The previous Government (2000-2005) had, therefore,
opted to corporatise CEB as a vertically integrated company and to retain CEB
in Government ownership. In 2004 and 2005 the enabling legislation was enacted
to provide the legal basis for these reforms, but these acts have not been
promulgated yet. At present the corporatisation of CEB does not fall under the
priorities of the new government.
The previous Government also wanted to
introduce an independent multi-sector 'Utility Regulatory Authority' to oversee
sector development. Draft legislation was put in place but not yet promulgated
and the utility regulator is yet to be formed.
Even though CEB operates today as a
vertically integrated utility-which means that it bears responsibility for the
full range of electricity services, including generation - a notable feature
of both the previous and new Governments' reform process is the move towards a
more competitive electricity generation sector, with both CEB and
private sector participating in the generation of electricity.
Independent Power Producers (IPPs)
Mauritius has had private power generators
since electricity was first available on the island. Since the 1990s, this
private sector participation has been formalised through policy directives,
such as the Bagasse Energy Development Program which gave rise to an increased
number of seasonal independent power producers (IPPs) at sugar estates
scattered around Mauritius and, since the late 1990s, through the signing of
power purchase agreements (PPAs) with FUEL Steam and Power Generation Co.
(FUEL), Consolidated Energy Ltd. (CEL), and Compagnie Thermique de Belle Vue
(CTBV). The result is that today virtually all bagasse from sugar processing on
the island is burned for electricity generation and cogeneration purposes.
The previous government was committed to
give the private sector an important role to play in the development of
electricity facilities with a view to freeing up precious public funds for
needed improvements in social services such as education, health care,
sanitation, etc. The new Government is, however, taking a cautious approach to
sector reform by maintaining vital infrastructure, such as the electricity
network, in the hands of CEB and put a rational share of electricity generation
in the hands of CEB. Development, expansion, and operation of the transmission
and distribution network will remain solidly in CEB's hands. What CEB will do
is to ensure equal access to the network to all generators in Mauritius and,
monitoring capacity and contractual constraints, move to a practice of
least-cost dispatch based on the marginal cost of generation. This will produce
more transparent and cost-effective operations for the benefit of all
electricity customers and suppliers.
Government and CEB have been doing their
part to create an atmosphere conducive to private sector investment by, for
example, introducing a transparent and competitive Request for Proposals
process for acquiring new power generation resources. The new government is
also moving to diversify private sector participants in the electricity
generation sector, which has heretofore been dominated by the sugar sector
seeking to optimize the use of bagasse as fuel.
Hand in hand with more private sector
development of new generation, CEB will still retain the ability to implement
its own generation and to redevelop or introduce efficiency improvements at its
existing facilities, should this prove to be more cost effective for
electricity consumers.
Power Purchase Agreements
CEB has power purchase agreements (PPAs)
with three take-or-pay IPP plants FUEL, CEL , and CTBV and the two-part tariff
IPP plants Compagnie Thermique du sud (CTDS) and the future Compagnie Termique
de Savannah (CTSav). Following the December 2002 Request for proposals, CEB
reached agreement with CTDS in 2003, for the supply of electricity from a 30 MW
coal-fired steam plant. Before the agreement was reached CEB carried out an
evaluation exercise and, entered into a predevelopment agreement and
negotiations respectively with CTDS. CEB and Compagnie Thermique du Sud (CTDS)
finally signed a power purchase agreement on 15 October 2003. Under the terms
of this agreement, Compagnie Thermique du Sud would be fully operational no
later than October 2005. This was duly respected. Another request for proposals
was issued in December 2003 for 60 MW to 70 MW of new generating capacity fired
by bagasse and a complementary fuel. After evaluation Compagnie Thermique de
Savannal Limitée (CTSav), with 65.5 /74 MW of capacity at delivery point
during Crop/Intercrop respectively was found to be the preferred bidder.
Negotiations were held from August 2004 to December 2004. The Power purchase
Agreement was eventually signed with CTSav in February 2005. Under the terms of
this agreement, CTSav will be fully operational in 2007.
CEB also has power purchase agreements with
seven IPPs that produce electricity from bagasse during the crop season only.
The capacity from the seasonal IPPs is 39 MW and is vital to CEB as it offsets
the crop-season reduction in capacity from the other year-round IPPs. In 2002,
CEB and the seasonal IPPs renegotiated their PPAs. A modification to the price
indexation formula has produced and will continue to produce considerable cost
savings for CEB each year. At the same time, some operational procedures, which
had been practised by tacit agreement, were formalised in the contracts. Over
the five or six years that most of these seasonal IPPs have been operating
under contract, they have successfully improved their operational efficiency,
with the result that they are able to deliver more electricity to CEB from
their supplies of bagasse.
Conclusion
To succeed as a viable business and to
ensure a stable electricity future in line with the economic needs of our
growing population, CEB will continue to rely on the private sector and IPP
projects for new supply of energy and capacity, while continuing to invest in
electricity generation to maintain an important share in power generation
sector in Mauritius. I strongly believe that there is still room to improve any
future power purchase agreements so that CEB can have greater flexibility to
operate the power system in a least-cost, efficient manner, and allocate risk
appropriately. I also believe that before pursuing additional electricity
generation projects, CEB must evaluate both build and buy alternatives to find
the best solutions for Mauritius. Any IPP program in Mauritius must reconcile
at least the following three objectives:
- Reduce electricity costs through competitive capacity
addition;
- Attract outside capital to meet growing electricity
needs without imposing constraints on internal financial capabilities; and
- Assign risks in an efficient manner.
In my opinion the new government will try
to keep the generation ratio of around 60% CEB and 40 % IPP, but in any
scenario with independent power suppliers connected with CEB's power system, it
is very important to ensure that each generator begins to share the
responsibility for reliability and security of supply. Suppliers must be fully
aware of our needs and expectations for power generation.
Copyright 2006© Institute for
Public-Private Partnerships, Inc. All rights reserved
Home |
About IP3 |
Training |
Consulting
Alumni
Corner | e-Newsletter | Careers |
Site Index |
Links |
Contact
|